Hi,
I have a bit of problem with DPM as the data is growing it is taking longer and longer for recovery point and tape backup.
I changed Max Parallel Job to 3 to run and finish quicker but it does not run parallel in my 2 node cluster. When I change it back to 1. it does throw an error "
DPM could not find a valid recovery point on disk. " There is no way I could set sequence on it. It is too moody to stick with the sequence as DataSourceGroups.xml file. Is there a way to make it better and faster . Where am I going wrong for parallel jobs?
I have already gone through few sites including this.
https://social.technet.microsoft.com/Forums/en-US/c40fa9f4-0162-410b-bb4b-ac4e3c576746/clarification-please-on-what-dpm-could-not-find-a-valid-recovery-point-means?forum=dpmtapebackuprecovery